Project metrics confirm performance

The governing body of the ITER Organization, the ITER Council, met for the twenty-first time on 15 and 16 November 2017 under the chairmanship of Won Namkung (Korea). Representatives from China, the European Union, India, Japan, Korea, Russia and the United States reviewed a detailed set of reports and indicators covering both organizational and technical performance, and concluded that the project remains on track for success.

In November 2007—ten years ago exactlythe ITER Council convened for the first time in the history of the ITER Organization. Clearing had just begun on the ITER site, the ITER design was under review, and only 170 people were working in temporary offices, housed by ITER's host and neighbourthe CEA Cadarache research centre.

Twenty Council meetings later and a quantum leap forward, the ITER Organization assesses the level of manufacturing completion for First Plasma components and systems at 61 percent and the level of total construction work scope completion through First Plasma at 49 percent.

Since early 2016, the ITER Organization has been controlling and reporting project progress on the basis of high-level milestones. Whether related to construction, manufacturing or deliveriesor rather to programmatic milestones like recruitment and contract signaturesthese milestones are underpinned in the schedule by the many thousands of activities that make up progress to First Plasma, with each one representing a firm achievement on the road to ITER operation.

During the two-day meeting, participants confirmed that the ITER Organization and the Domestic Agencies have achieved all Council-approved milestones for 2016 and 2017, maintaining strict adherence to the overall project schedule and critical path. Processes for schedule control, risk management and cooperation also continue to improve, with project performance metrics that now measure physical progress in construction, manufacturing, assembly and installation down to the level of each building system and component.

The Council continued its candid discussions acknowledging continuing efforts made by each Member to overcome various challenges, which include ensuring approval of the cost baseline, as concluded at the Nineteenth ITER Council in November 2016 (IC-19¹). Council members reaffirmed their strong belief in the value of the project, and its mission and vision, and resolved to work together to find timely solutions to ensure ITER's success.

ITER Communication





25.06.2018
The ITER Council, ITER's governing body, met for the twenty-second time on 20 and 21 June 2018 at the ITER Organization in Saint Paul-lez-Durance, France. Council Members approved refinements to the construction strategy which will optimize the installation of components in the Tokamak Complex. With this strategy in place, the project is on track to achieve First Plasma in 2025 while adhering to overall project costs
19.06.2018
In June, Russia has officially completed its second Procurement Arrangement within the framework of the ITER Project joint implementation ploidal field conductors for the ITER magnet system have been fabricated in full scope
13.06.2018
Within the scope of Russian obligations within the ITER Project in-kind contribution, the largest, for the moment, pack of the Russian electrotechnical equipment for the future facility has been successfully delivered to France
29.05.2018
In mid-May, factory acceptance tests of the second Russian Gyrotron set for the ITER machine were carried out by specialists of the Institute of Applied Physics of the Russian Academy of Sciences and GYCOM Ltd. (Nizhny Novgorod)
09.04.2018
Series of tests of the Switching Network Unit (SNU) prototype for the ITER coil power supply systems, within the scope of Russian obligations, successfully conducted at the Efremov Institute in St. Petersburg
02.04.2018
April 2, 2018, progress of the Russian participation in the ITER Project was reported at the ITER Project. Step to future energy section under supervision of Anatoly Krasilnikov director of the institution Project Center ITER (Russian ITER DA) within the framework of the 45th International Zvenigorod Conference on plasma physics and controlled fusion
12.09.2017
September 7, six trucks with elements of direct current aluminum busbars for ITER superconducting magnet power supply moved to the sea port of Saint Petersburg for further transportation to the ITER construction site
26.06.2017
On 24 October 2007, the ITER Organization was officially established following the ratification by the seven ITER Members of the project's constitutive document, the ITER Agreement.
Now, nearly ten years on, a unique community has taken root in southern France, among the hills of Haute Provence. Hundreds of scientists, engineers, technicians, project members and administrators from 35 countries that are working toward the same goal: building the first machine that will be capable of demonstrating a burning plasma, a self-sustaining environment that holds the key to the development of a new, safe, environmentally responsible and virtually inexhaustible energy source.
13.02.2017
February 13, 2017, traditionally, the ITER: step to future energy section under supervision of Anatoly Krasilnikov director of the institution Project Center ITER (Russian ITER DA) took place within the framework of the 44th International Zvenigorod Conference for plasma physics and thermonuclear fusion
News 1 - 10 149
 | . | 1 2 3 4 5 6 7 8 9 10 11 | . |  |  

News archive