Project metrics confirm performance

The governing body of the ITER Organization, the ITER Council, met for the twenty-first time on 15 and 16 November 2017 under the chairmanship of Won Namkung (Korea). Representatives from China, the European Union, India, Japan, Korea, Russia and the United States reviewed a detailed set of reports and indicators covering both organizational and technical performance, and concluded that the project remains on track for success.

In November 2007—ten years ago exactlythe ITER Council convened for the first time in the history of the ITER Organization. Clearing had just begun on the ITER site, the ITER design was under review, and only 170 people were working in temporary offices, housed by ITER's host and neighbourthe CEA Cadarache research centre.

Twenty Council meetings later and a quantum leap forward, the ITER Organization assesses the level of manufacturing completion for First Plasma components and systems at 61 percent and the level of total construction work scope completion through First Plasma at 49 percent.

Since early 2016, the ITER Organization has been controlling and reporting project progress on the basis of high-level milestones. Whether related to construction, manufacturing or deliveriesor rather to programmatic milestones like recruitment and contract signaturesthese milestones are underpinned in the schedule by the many thousands of activities that make up progress to First Plasma, with each one representing a firm achievement on the road to ITER operation.

During the two-day meeting, participants confirmed that the ITER Organization and the Domestic Agencies have achieved all Council-approved milestones for 2016 and 2017, maintaining strict adherence to the overall project schedule and critical path. Processes for schedule control, risk management and cooperation also continue to improve, with project performance metrics that now measure physical progress in construction, manufacturing, assembly and installation down to the level of each building system and component.

The Council continued its candid discussions acknowledging continuing efforts made by each Member to overcome various challenges, which include ensuring approval of the cost baseline, as concluded at the Nineteenth ITER Council in November 2016 (IC-19¹). Council members reaffirmed their strong belief in the value of the project, and its mission and vision, and resolved to work together to find timely solutions to ensure ITER's success.

ITER Communication





12.09.2017
September 7, six trucks with elements of direct current aluminum busbars for ITER superconducting magnet power supply moved to the sea port of Saint Petersburg for further transportation to the ITER construction site
26.06.2017
On 24 October 2007, the ITER Organization was officially established following the ratification by the seven ITER Members of the project's constitutive document, the ITER Agreement.
Now, nearly ten years on, a unique community has taken root in southern France, among the hills of Haute Provence. Hundreds of scientists, engineers, technicians, project members and administrators from 35 countries that are working toward the same goal: building the first machine that will be capable of demonstrating a burning plasma, a self-sustaining environment that holds the key to the development of a new, safe, environmentally responsible and virtually inexhaustible energy source.
13.02.2017
February 13, 2017, traditionally, the ITER: step to future energy section under supervision of Anatoly Krasilnikov director of the institution Project Center ITER (Russian ITER DA) took place within the framework of the 44th International Zvenigorod Conference for plasma physics and thermonuclear fusion
05.12.2016
On Monday, December 5th, a floatboard with the pack of Switching Network for the International Thermonuclear Experimental Reactor left the sea port of Saint-Petersburg
18.11.2016
During the Nineteenth Meeting of the ITER Council held last week from 16 to 17 November, representatives of the ITER Members reviewed the complete updated project schedule as proposed by the ITER Organization. The schedule, which covers the period up to First Plasma in 2025 and on to Deuterium-Tritium Operation in 2035, was approved by all Members
02.11.2016
November 2, Director General of the ITER Organization Bernard Bigot payed a one-day visit to the Russian ITER Domestic Agency
10.10.2016
On Monday, October 10, 2016, the Russian ITER Domestic Agency welcomed the 1st and 2nd year students of the Department of Problems of Physics and Energetics (DPPE), Moscow Institute of Physics and Technology (MIPT)
03.10.2016
Dear colleagues,
this is to inform you that the following open positions will be available at the ITER Organization
05.09.2016
In St. Petersburg specialists of the Efremov Institute and the Sredne-Nevsky Shipyard have completed winding of the superconducting double pancake for the poloidal field coil PF1 of the ITER magnet system